Contract-administration study guide comparing PAM, IEM, JKR Design & Build, and FIDIC, focusing on the five areas you listed.
Important: Exact clause numbers and response periods can differ by edition and by amendments/Particular Conditions. For an actual project, always check the signed contract documents. PAM publishes material on PAM Contract 2018, while FIDIC 2017 has its own General Conditions and Particular Conditions structure. (Pam)
1. Roles and Powers of Contract Administrator / Superintending Officer
The person administering the contract is important because they certify, instruct, assess, determine and administer the contract, but their powers depend on the particular form.
| Contract | Main administrator | Main function |
|---|---|---|
| PAM | Architect / Contract Administrator | Administers construction contract, issues instructions/certificates, assesses EOT, variations and payment |
| IEM | Engineer / Contract Administrator | Administers engineering contract, certifies work/payment, assesses claims and EOT |
| JKR D&B | Superintending Officer (S.O.) | Acts for Government/Employer in administering the contract and issuing directions/certificates |
| FIDIC | Engineer | Administers contract, gives instructions, determines matters and assesses claims |
A. PAM
The Architect normally has a central contract-administration role.
Typical powers include:
issue Architect's Instructions;
issue certificates;
assess variations;
assess extension of time;
certify payments;
inspect and evaluate the works;
certify practical completion;
administer defects;
assess contractual claims.
However, the Architect is not simply the Employer's agent in every matter. Contractual duties must be exercised according to the contract.
B. IEM
Under an IEM-type engineering contract, the Engineer performs many functions similar to the Architect under PAM.
The Engineer may:
issue instructions;
inspect works;
certify payment;
assess variations;
assess EOT;
evaluate claims;
administer completion and defects.
The important principle is:
Engineer ≠ Contractor's manager.
The Engineer administers the contract but does not normally take over the Contractor's responsibility for construction.
C. JKR Design & Build
The Superintending Officer (S.O.) has substantial administrative powers because this is a Government contract.
The S.O. may:
issue directions;
administer the works;
certify payments;
assess variations;
assess EOT;
inspect and monitor compliance;
certify completion;
administer contractual procedures.
JKR itself publishes guidance dealing with issues such as termination, practical completion, final accounts, variation, EOT and contract administration. (JKR Malaysia)
A key difference is that in Design & Build, the Contractor carries significant responsibility for both design and construction. The JKR DB/T form specifically includes provisions dealing with the Contractor's design responsibility. (pdfcoffee.com)
D. FIDIC
FIDIC uses the term Engineer.
The Engineer's role includes:
administering the Contract;
giving instructions;
evaluating work;
certifying payments;
dealing with claims;
making determinations where required.
FIDIC 2017 places considerable emphasis on formal claims, determinations and dispute avoidance. (FIDIC)
Easy exam point
Remember:
PAM → Architect
IEM → Engineer
JKR D&B → Superintending Officer
FIDIC → Engineer
2. Response Timeframes for Key Contract Clauses
This is one of the most important areas because failure to comply with contractual time limits can affect entitlement.
Common contractual notices
Typical matters requiring timely action include:
EOT claim;
variation;
payment certification;
claims;
notice of delay;
termination notice;
defects;
dispute notification.
FIDIC
FIDIC is particularly strict about formal claims.
Under the FIDIC 2017 system, claims are subject to prescribed notice and submission procedures. The 2017 contracts also apply claims procedures to both Employer and Contractor claims. (Wiley Online Library)
A commonly tested concept is:
28-day Notice of Claim
The Contractor generally needs to notify the Engineer within the contractual period after becoming aware of the event/circumstance giving rise to the claim.
Then:
Notice → particulars/evidence → assessment/determination
This is commonly called a time bar.
Why is the time bar important?
Suppose:
Delay occurs on 1 June.
Contract says notice must be given within 28 days.
Contractor gives notice on 15 July.
Potential consequence:
Late notice → loss/restriction of contractual entitlement, depending on the applicable FIDIC edition and Particular Conditions.
Therefore:
Construction team must identify a delaying event immediately, not wait until the project is already late.
3. Termination Clauses and Procedures
Termination means the contractual relationship is brought to an end before normal completion.
There are generally two broad categories:
A. Termination by Employer
Usually associated with serious Contractor default, such as:
abandonment;
failure to proceed with the works;
insolvency;
serious breach;
failure to comply with instructions;
persistent failure to perform.
B. Termination by Contractor
May arise because of serious Employer default, such as:
prolonged non-payment;
suspension caused by Employer;
serious breach by Employer;
other contractual grounds.
Typical termination procedure
A simplified procedure is:
Default occurs
↓
Notice of default
↓
Opportunity/cure period, where required
↓
Failure to remedy
↓
Termination notice
↓
Take-over / securing the site
↓
Measurement and valuation
↓
Final account / damages / costs
The exact procedure varies significantly between forms.
PAM
PAM contains contractual mechanisms for termination for specified defaults. The Architect/Employer must follow the contractual procedure rather than simply saying:
"The Contractor is terminated."
Procedural compliance is critical.
JKR D&B
Termination is particularly important in Government contracts.
The S.O. must follow the applicable contractual requirements before termination. The JKR D&B form contains specific contractual provisions governing the Contractor's obligations and the administration of the contract. (pdfcoffee.com)
FIDIC
FIDIC provides detailed termination mechanisms and distinguishes between different grounds for termination.
Exam point:
Termination is a contractual remedy and must be exercised according to the contract.
4. EOT, LAD and Project Timeline
This is probably the most important relationship to understand.
Extension of Time (EOT)
EOT means:
The Contractor receives additional contractual time to complete the works.
Example:
Original completion date:
31 December 2026
A qualifying Employer-risk delay causes:
60 days delay
Approved EOT:
60 days
New completion date:
1 March 2027 approximately.
Therefore, the Contractor is not late if completion occurs within the revised contractual completion date.
Typical reasons for EOT
Depending on the contract, examples can include:
variation instructed by Employer;
late information/drawings;
exceptionally adverse weather;
delay caused by Employer;
force majeure / relevant events;
changes in statutory requirements;
other contractual Relevant Events.
The exact entitlement differs between PAM, IEM, JKR and FIDIC.
LAD — Liquidated Ascertained Damages
LAD is a pre-agreed contractual amount payable for delay, subject to the contract's requirements.
Example:
Contract:
LAD = RM20,000/day
Completion date:
31 December
Actual completion:
10 January
Delay:
10 days
Potential LAD:
RM20,000 × 10 = RM200,000
But there is an important step:
First determine the correct completion date.
If the Contractor is entitled to 10 days EOT:
Original completion:
31 December
EOT:
10 days
=
Revised completion date: 10 January
Therefore:
Actual completion = 10 January
LAD = RM0
EOT and LAD relationship
Think of it like this:
Delay event
↓
Is Contractor entitled to EOT?
↓
Yes → revise completion date
↓
Compare actual completion with revised date
↓
Late?
↓
Yes → LAD may apply
This is why EOT assessment must be done properly before determining delay damages.
5. Dispute Resolution Mechanisms
Disputes occur when the parties disagree about things such as:
payment;
variations;
EOT;
LAD;
defects;
termination;
valuation;
interpretation of contract clauses.
Different forms use different dispute-resolution structures.
PAM
A typical progression is:
Contract administration
↓
Negotiation / discussion
↓
Adjudication
↓
Arbitration / court,
depending on the contract and applicable law.
In Malaysia, statutory adjudication under CIPAA 2012 can also become relevant to construction payment disputes where its requirements apply.
IEM
The IEM form generally provides contractual mechanisms for resolving disputes, potentially involving:
Engineer / Contract Administrator
↓
Negotiation / contractual determination
↓
Adjudication / arbitration
The exact route depends on the particular IEM form and amendments.
JKR D&B
For Government projects, disputes are dealt with according to the contractual dispute mechanism and applicable Malaysian law.
The important principle for examination is:
The Contractor should use the contractual dispute procedure rather than immediately abandoning performance or taking unilateral action.
FIDIC — Important Exam Structure
FIDIC 2017 has a particularly structured dispute system.
The 2017 Red Book includes:
DAAB — Dispute Avoidance/Adjudication Board
dispute avoidance;
DAAB decision;
amicable settlement;
arbitration.
FIDIC's official description specifically identifies the DAAB and dispute-avoidance mechanisms. (FIDIC)
The sequence can be remembered as:
DAAB → Amicable Settlement → Arbitration
More completely:
Dispute arises
↓
Dispute avoidance / Engineer's determination
↓
DAAB
↓
DAAB decision
↓
Amicable settlement
↓
Arbitration
FIDIC 2017 expressly structures Clause 21 around DAAB constitution, dispute avoidance, obtaining a DAAB decision, amicable settlement and arbitration. (www.slideshare.net)
Overall Comparison
| Issue | PAM | IEM | JKR D&B | FIDIC |
|---|---|---|---|---|
| Administrator | Architect | Engineer | S.O. | Engineer |
| Contract type | Building | Engineering/construction | Government D&B | International construction |
| Design responsibility | Usually Employer's design | Depends on form | Contractor | Depends on FIDIC Book |
| EOT | Contractual EOT procedure | Contractual EOT procedure | S.O. assesses under JKR conditions | Formal claims procedure |
| LAD | Yes, if provided | Yes, if provided | Yes | Delay damages under contract |
| Claims | Formal contractual process | Formal process | Formal Government procedure | Highly structured |
| Notice/time bar | Important | Important | Important | Very important |
| Dispute | Contractual mechanism/CIPAA where applicable | Contractual mechanism | Government contractual mechanism | DAAB → settlement → arbitration |
⭐ Key Exam Concepts to Memorise
1. Contract Administrator
Administers the contract, but does not take over the Contractor's responsibility.
2. Notice
A contractual claim must be notified within the required period.
3. EOT
EOT changes the contractual completion date.
4. LAD
LAD is assessed by reference to the applicable contractual completion date.
5. Termination
Termination must follow the contractual procedure and grounds.
6. Dispute
Use the contract's dispute-resolution mechanism before escalating to arbitration/litigation.
7. FIDIC
DAAB is central to the 2017 dispute mechanism.
8. JKR D&B
The Contractor has major responsibility for both design and construction.
Simple flow to remember for an exam
DELAY
→ Contractor gives NOTICE
→ Contract Administrator/Engineer assesses EOT
→ Completion Date is revised
→ If Contractor still finishes late
→ LAD may apply
If there is disagreement:
→ CLAIM
→ DETERMINATION
→ DISPUTE RESOLUTION
→ ADJUDICATION / DAAB / ARBITRATION, depending on the contract.
The biggest practical lesson is that contract administration is time-sensitive: notices, EOT claims, certificates, termination notices and dispute referrals must all follow the particular contract's prescribed procedure. FIDIC, in particular, formalises claims and dispute avoidance in considerable detail. (Wiley Online Library)
No comments:
Post a Comment